People ask how long a dinosaur takes. It is a fair question with an awkward answer: it depends on the size, on how many movements, on what else is on the floor that month, and on the day you approve the drawings.
What does not depend on any of those things is where the time goes.
Here is our actual split. Eight stages, and they add up to 100%.
Proportions below are our own production, measured across builds. Other factories and other specifications will land differently.
1 · Steel frame · 30%
Three tenths, and it earns them
This stage covers four jobs. Cutting tube and plate to the dimensions and angles on the CAD drawing. Building the transmission — telescopic rods, eccentric wheels, machined parts — sized to the arc each movement actually travels. Placing the motors where they can drive the structure without pushing the silhouette out of shape, then checking the current balance. And finally, pushing the whole frame into the booth for rust treatment.
Why does it take the longest? Because it is the one stage where a change means going back to the start.
Two centimetres out on a dimension, three degrees out on a joint — and you do not find out until the foam is on. At that point it is not a frame problem. It is a rebuild.
So a good part of that 30% is not building. It is measuring, checking, and testing.
2 · Electrical wiring · 10%
A tenth of the time, three details that matter later
Wiring is a tenth because this stage follows the structure rather than leading it. Three details inside it are specific to this kind of product.
Where the cables come out
Every motor cable leaves from under the leg closest to the tail, ends in a quick-release connector, and goes on to the controller. Position sensors and limit switches take the same route.
The quick-release part matters because the body ships in sections. Whether a site can reconnect it in an afternoon or spends a week on it comes down to that one connector.
The cable bridge
Where a bundle has to cross a working joint, a steel rope runs through the middle, the bundle is wrapped, and the whole thing becomes a reinforced bridge.
The reason is fatigue. A neck moves thousands of times a day; the bundle bends with it thousands of times; copper work-hardens and breaks at the same point. With the rope inside, the rope takes the bending and the copper rides along. Without it, roughly half a year later the movement starts working intermittently.
The current balance test
This one happens while the frame is still bare — checking that the current draw is even through left, right, up and down, and leaving headroom for what comes next.
At this point the machine is naked. Once tens of kilos of foam and silicone are on it, the load changes, and the current changes with it. The headroom is for the skin, not for now.
3 · Artwork and sculpting · 20%
Part of that fifth is set aside for rework
Three jobs sit in this stage: building up enough foam over the frame, carving the shape, and revising it.
The third one gets its own line because it does not appear on most quotations.
Carving is hand work. Halfway through, a proportion reads wrong, or a muscle runs in a direction that does not convince, and it gets redone. That is normal rather than exceptional. Writing the time into the quotation is more honest than adding it afterwards — and this is also the stage that decides whether the animal looks alive. Whatever the sculptor can feel ends up in that layer of foam.
4 · Skin making · 20%
Half of it is waiting for silicone to dry
The sequence runs like this. Press wrinkles and texture grooves into the foam. Brush on silicone and lay in a layer of fibre cloth. Coat the whole surface in silicone and leave it to skin over for 12 hours. Second coat, another 12 hours.
So a good share of that 20% is waiting rather than working. Silicone goes on one layer at a time. Put the next coat on before the last one has cured and it bubbles or delaminates, and repairing that costs more than starting again.
It is also why a build cannot be shortened by adding people. You can add hands. You cannot add drying time.
5 · Painting · 5%
Five percent, and it needs two poses
Base colour all over first, then let it flash off.
Then the step that decides the result: open the mouth to its limit, tilt the head back, set the body at the angle people will look from, and cover everything the first pass could not reach.
The reason is plain enough. With the mouth closed, the inside of it cannot be painted. With the head down, the underside of the jaw cannot be painted. Those are exactly the angles visitors end up photographing.
6 · Full-unit testing · 8%
Twenty-four hours without stopping
Every unit runs for at least 24 continuous hours before it ships. Continuous means no shutdown, no pause in the movement — just running.
The point is to keep faults that would appear on installation inside the factory, instead of on your opening day.
Eight percent is not a small slice. We think it is the right trade: finding a fault here and finding the same fault in another country are not the same cost.
7 · Disassembly, packing, loading · 6%
Turning a finished animal back into freight
Large models ship in sections, which means splitting joints, labelling what connects to what, packing, and securing it all.
The stage looks like packing and gets underestimated for that reason. What it actually is: turning a finished animal back into something that fits through a container door, survives a month at sea, and reassembles on the other side without a workshop.
The last of the eight stages is only one percent — fitting the decorative parts. Teeth, tongue, eyes, claws. Small items, all hand-fitted, and the difference between a model that reads as an animal and one that reads as a machine.
If the date is tight
Three levers, and what each one costs
There are three ways to compress a build. We will pull any of them. Each one has a price, and it is better stated now than discovered later.
Overtime
Beyond the normal eight-hour day, an evening shift from 18:00 to 23:00.
Compressed commissioning
Less time on setup, parameter tuning and repeated test runs.
You staying reachable
This one does not sound like a method, and it is the most effective of the three. Most of the delays we see are not slow machining — they are a waiting confirmation. A drawing revision. A colour. Whether a movement should be added. When the person who decides can decide on the spot, weeks come off the schedule.
We do not push any of these unless the date is genuinely fixed. The reason is simple. Overtime compresses the part that involves people; it cannot compress drying, and it cannot compress the run test. And whatever gets cut from commissioning usually reappears on site — where it is your budget paying for it.
Rush jobs we take. We just lay all of this out first.
Have a date in mind?
Send it with the specification — size, movements, quantity. We will come back with a realistic build window, tell you which of the three levers it would take, and what each one costs.
Send us the spec